Glacier Sands Wind Farm is an 184.9MW onshore wind power project. It is located in Illinois, the US. The project is currently active. It has been developed in single phase. The project construction commenced in 2020 and subsequently entered into commercial operation in December 2021.

Project Type Total Capacity (MW) Active Capacity (MW) Pipeline Capacity (MW) Project Status Project Location Project Developer
Onshore 184.9 184.9 Active Illinois, the US Cordelio Power; Swift Current Energy

Description

How well do you really know your competitors?

Access the most comprehensive Company Profiles on the market, powered by GlobalData. Save hours of research. Gain competitive edge.

Company Profile – free sample

Thank you!

Your download email will arrive shortly

Not ready to buy yet? Download a free sample

We are confident about the unique quality of our Company Profiles. However, we want you to make the most beneficial decision for your business, so we offer a free sample that you can download by submitting the below form

By GlobalData
Visit our Privacy Policy for more information about our services, how we may use, process and share your personal data, including information of your rights in respect of your personal data and how you can unsubscribe from future marketing communications. Our services are intended for corporate subscribers and you warrant that the email address submitted is your corporate email address.

The project was developed by Cordelio Power and Swift Current Energy. The project is currently owned by Cordelio Power.

The project cost is $275m.

Development Status

The project is currently active. The project construction commenced in 2020 and subsequently entered into commercial operation in December 2021.

Power Purchase Agreement

The power generated from the project is sold to Microsoft under a power purchase agreement for a period of 15 years from 2021. The contracted capacity is 184.9MW.

Contractors Involved

White Construction was selected to render EPC services for the wind power project.

Vestas Wind Systems was selected as the turbine supplier for the wind power project. The company provided 43 units of V150-4.3 MW turbines, each with 4.3MW nameplate capacity.

About Cordelio Power

Cordelio Power Inc (Cordelio), a subsidiary of Canada Pension Plan Investment Board, is an independent power producer that develops, finances, builds and operates renewable energy power plants. The company offers services such as project management, engineering, procurement and construction; and operation and maintenance of renewable energy power plants. It generates electricity from various renewable energy sources including hydro, solar and wind. Cordelio owns and operates thermal and renewable power projects across North America. The company has operational presence in the US. Cordelio is headquartered in Toronto, Ontario, Canada.

About Swift Current Energy

Swift Current Energy LLC (Swift Current Energy) develops and manages energy projects. The Company focuses on utility scale wind, solar, and energy storage power projects. It is headquartered in the US.

Methodology

All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.