Share

The Inowroclaw FGD final acceptance protocol has been signed on 7 December 2017.

Previous critical project milestones included the FGD plant being handed over (PAC) on the scheduled date of 19 July 2017.

A trial run started on 16 May 2017 at 18:00 and was successfully completed on 17 June.

The project execution began on the contract signing date of 27 July 2015.