The Aghios Dimitrios service agreement between J&P Avax and Sirius Engineers was signed on 9 August last year.
Kick off meetings with both the Employer PCC and Contractor J&P were held in Athens, Greece.
J&P Avax signed the main contract with Public Power Company (PPC) on 30 June and project time is running.
The basic design was due to be completed by the end of last year and PAC shall be completed in June 2020 according to the agreement.
Sirius is acting as FGD technology supplier for general contractor J&P Avax.
J&P and Sirius were awarded the contract from PPC after the prequalification and tendering process according to the public tendering procedure.