M.IN.T.OR. has received a contract to supply a heat recovery steam generator, in particular a CO Boiler designed by Foster Wheleer Italiana, for the final user Saras Refinery.
The Co Boiler has a capacity of 130 t/h at 72.5 barg and 490°C.
The scope of the contract consists of detailed engineering, supply material, construction of steel casing and piping, refractory lining, NDT, painting and delivery.
The boiler has been designed in ten modules / skid, which have an average weight of 80t each. These will be manufactured in six months, working on three shifts per day, seven days per week.
The first five modules will be shipped within the first decade of September.