Weld repairing six descale box table bearing pockets in 96 total elapsed hours takes creativity, planning and flawless execution. Field System Machining recently completed this project for one of our perennial steel mill customers.
Fixturing is everything on a compressed schedule outage. Successful on-site steel mill outage work happens partly in the shop prior to arrival. When you have 33 years of steel mill turnaround and steel mill repair experience you know that careful preparation means on-time completion in the field; 267 shop man hours of preparation went into manufacturing fixtures for this project.