The 150MW Burgos wind farm in Ilocos Norte is the biggest wind farm in the Philippines and the first wind project nominated for the Philippine Government’s feed-in-tariff (FIT) incentive scheme.
The onshore wind farm was commissioned in November 2014 and is owned and operated by the EDC Burgos Wind Power Corporation (EBWPC), an affiliate of Energy Development Corporation (EDC).
Development included the 87MW first phase and the 63MW second phase. The groundbreaking ceremony was held in April 2013 and the construction works began in June of the same year.
The wind farm generates approximately 370GWh of electricity a year, which is used to power more than two million households. It offsets approximately 200,000t of CO₂ emissions annually.
The Burgos wind farm project was awarded the 2015 Asia Power Engineering International Best Renewable Energy Project for achieving five million safe man-hours without incident.
Burgos wind project site and development details
The Burgos wind project is located approximately 500km north of Manila and spread across a 686ha area, covering Saoit, Nagsurot and Poblacion barangays within the Municipality of Burgos in Ilocos Norte Province, northern Philippines.
The Philippine Department of Energy (DOE) nominated the project to the country’s Energy Regulatory Commission (ERC) as an eligible project under the FIT programme, which allows a renewable energy development company to receive guaranteed payments from the ERC on a fixed rate per kilowatt-hour basis.
Burgos wind farm design and features
Burgos consists of 50 Vestas V90 wind turbines with a rated capacity of 3MW each.
The first phase included the installation of 29 wind turbines and the construction of a wind farm substation, 13.6km access roads and a 42km overhead transmission line. The remaining 21 turbines were installed in the second phase.
Each wind turbine rests on a tubular steel tower, has a 75m hub height and a 90m rotor diameter and offers a swept area of 6,326m². The wind turbine generators are expected to have an average lifecycle of 20 years.
Approximately 630m³ of concrete was used for the construction of foundations for each wind turbine tower.
The project also included a Yaw back-up generation system, consisting of three 1.5MW units to provide back-up power. The system was installed to use in the event of a power failure and to turn the turbine rotor against the wind.
Transmission of power from the Burgos wind farm
Power from the substation is sent through a 115kV single-circuit overhead transmission line to the National Grid Corporation of the Philippines (NGCP) substation in Laoag City, from where it is then transmitted to the Luzon grid.
The 43km-long transmission line to the Laoag substation passes through the Burgos, Pasuquin, Bacarra and Laoag municipalities and consists of 147 structures, including 127 lattice steel towers and 20 steel poles.
Financing of the wind project
The cost of the Burgos wind farm was estimated to be $450m. EDC secured $315m in debt financing from a group of foreign and local banks in October 2014. The debt financing facility consists of US dollars and Philippine peso tranches, which will expire in 15 years. The Asian Development Bank approved a senior secured term loan of $20m to EDC in November 2015 as part of the debt financing facility.
Danish export credit agency Eksport Kredit Fonden (EKF) provided a guarantee for a portion of the US dollar loan component and the Australia and New Zealand Banking Group (ANZ), DZ Bank, the ING Bank, Malayan Banking Berhad (Maybank) and Norddeutsche Landesbank Gironzentrale acted as mandated multiple lead arrangers for the foreign tranche.
The local tranche for the loan facility was arranged by PNB Capital and Investment Corporation and SB Capital Investment Corporation, along with a group of local lenders, including BDO Unibank, Land Bank of the Philippines, Philippine National Bank and Security Bank Corporation.
Contractors for the Burgos wind farm
Denmark-based Vestas Wind Systems supplied and installed 50 V90-3.0MW turbines for the project. The company also provided associated onsite civil and electrical works for the project and will operate and maintain the wind farm under a ten-year operations and maintenance (O&M) agreement.
First Balfour was sub-contracted by Vestas for the engineering, procurement and construction of civil works, as well as 120km of electrical cabling.
The company was also contracted by the EDC for the detailed engineering, design, construction and installation of the 43km-long, 115kV overhead transmission line.
WSP was appointed as the owner’s engineer to provide and monitor technical support for the project.