Tekmar Energy has delivered cable protection systems (CPS) for the installation of 200 miles (328 km) of 66KV inter-array cables at Dogger Bank A. This is a crucial phase in the construction of the world’s largest offshore wind farm on the east coast of England.

The sophisticated operation involves DEME Offshore’s cable-laying vessel Viking Neptun and burial operations by the Living Stone.

The network will comprise 95 cables, some running 8.6 miles (13.8 km), linking Dogger Bank A’s 95 Haliade-X 13MW turbines to the offshore converter station.

The generated electricity is converted to direct current through an advanced high-voltage direct current system, then transmitted to the onshore converter station.

Tekmar Energy’s role has been pivotal, providing the cable protection systems that shield the inter-array cables from damage and ensure their long-term reliability.

Tekmar Energy managing director Marc Bell stated, “We are incredibly proud to support the Dogger Bank wind farm with our advanced cable protection systems. This project showcases our commitment to innovation and excellence in the offshore wind sector. The successful completion of this phase is a testament to our strong partnership and collaborative effort.”

How well do you really know your competitors?

Access the most comprehensive Company Profiles on the market, powered by GlobalData. Save hours of research. Gain competitive edge.

Company Profile – free sample

Thank you!

Your download email will arrive shortly

Not ready to buy yet? Download a free sample

We are confident about the unique quality of our Company Profiles. However, we want you to make the most beneficial decision for your business, so we offer a free sample that you can download by submitting the below form

By GlobalData
Visit our Privacy Policy for more information about our services, how we may use, process and share your personal data, including information of your rights in respect of your personal data and how you can unsubscribe from future marketing communications. Our services are intended for corporate subscribers and you warrant that the email address submitted is your corporate email address.

Tekmar Group’s business unit, RYDER, undertook the Orcaflex analysis and geotechnical design for the project. This ensured optimal protection and installation of the cables in challenging offshore conditions.

Tekmar Energy project manager Liam Bettinson stated, “Providing the cable protection systems for the Dogger Bank A installation phase is a remarkable achievement for our team. It required meticulous planning, innovative engineering and flawless execution. I am proud of our team’s dedication and the successful collaboration with our partners, which has laid a strong foundation for the subsequent phases of Dogger Bank B and C.”

The installation followed extensive underwater surveys to secure a clear cable-laying corridor, marking a major achievement in the inter-array cable installation programme – the largest of its kind in offshore wind energy to date.