Voith Hydro

Voith has completed work on the 95MW Budarhals hydro power plant in Iceland. The project has been commissioned during an opening ceremony on 7 March 2014, which was held by Voith and Landsvirkjun, the national power company in Iceland.

The company has supplied and installed two Kaplan turbines, which has water-filled runner hubs. It also provided generators with the latest technology using brushless thyristor controlled exciters.

Voith’s project work also included the supply of powerhouse cranes and station control systems.

Landsvirkjun Budarhals project manager Gudlaugur Thorarinsson said, “All works on the project has been diligently completed in spite of harsh winter weathers and an ambitious time schedule, while the company is satisfied with the performance of Voith.”

Successful completion of the project represents a long term continuation of business activity in Iceland, Voith said.

The first design for the Budarhals hydropower plant was performed by Landsvirkjun in 1989 and later developed to the present design.

How well do you really know your competitors?

Access the most comprehensive Company Profiles on the market, powered by GlobalData. Save hours of research. Gain competitive edge.

Company Profile – free sample

Thank you!

Your download email will arrive shortly

Not ready to buy yet? Download a free sample

We are confident about the unique quality of our Company Profiles. However, we want you to make the most beneficial decision for your business, so we offer a free sample that you can download by submitting the below form

By GlobalData
Visit our Privacy Policy for more information about our services, how we may use, process and share your personal data, including information of your rights in respect of your personal data and how you can unsubscribe from future marketing communications. Our services are intended for corporate subscribers and you warrant that the email address submitted is your corporate email address.
“Voith’s project work also included the supply of powerhouse cranes and station control systems.”

Following the economic and financial crisis in 2008, Budarhals was the first major infrastructure project being built.

Voith Financial Services financing structure was an important support for the hydropower project, as it assisted Landsvirkjun in funding.

According to the ‘World Atlas Hydropower & Dam 2013’, with Budarhals hydroelectric project Iceland has total installed hydro capacity of 1,980MW.

In 2011, hydropower plants have contributed approximately 73% to the national electricity output by generating 12,507GWh of power.


Image: A winter landscape with the hydropower plant Budarhals, Iceland. Photo: courtesy of Landsvirkjun.