Construction of Barakah Nuclear Energy Plant's first unit has been completed in the United Arab Emirates (UAE) but operations have been postponed to 2018.

The Emirates Nuclear Energy Corporation (ENEC) and Korea Electric Power Corporation (KEPCO) finished construction activities this month and is ready for testing and commissioning by KEPCO's unit Korea Hydro and Nuclear Power (KHNP).

The key contract was awarded to KEPCO in 2009 for construction of the plant.

ENEC's chief executive officer (CEO) Mohamed Al Hammadi was quoted by Meconstructionnews.com as saying: “The completion of Unit 1 construction activities and the handover of all systems for commissioning are important milestones in a project that is critical to the future energy mix of the UAE and they reflect the professionalism and dedication of everyone involved in the project.”

According to UAE law, construction and commencement of operations in nuclear power facilities require approval by the Federal Authority for Nuclear Regulation (FANR). Approval is needed for loading of fuel and commencement of the unit in form of an operating license.

"ENEC has pursued the highest standards of nuclear quality, safety, and operational transparency."

While the ENEC has secured approval from its board of directors, the operations have been postponed from 2017 to 2018. This decision was taken to ensure sufficient time for international assessments and adherence to nuclear industry safety standards.

How well do you really know your competitors?

Access the most comprehensive Company Profiles on the market, powered by GlobalData. Save hours of research. Gain competitive edge.

Company Profile – free sample

Thank you!

Your download email will arrive shortly

Not ready to buy yet? Download a free sample

We are confident about the unique quality of our Company Profiles. However, we want you to make the most beneficial decision for your business, so we offer a free sample that you can download by submitting the below form

By GlobalData
Visit our Privacy Policy for more information about our services, how we may use, process and share your personal data, including information of your rights in respect of your personal data and how you can unsubscribe from future marketing communications. Our services are intended for corporate subscribers and you warrant that the email address submitted is your corporate email address.

Al Hammadi added: “Since 2009, ENEC has pursued the highest standards of nuclear quality, safety, and operational transparency.

“The approval of a timeline update projecting the initiation of Unit 1 nuclear operations in 2018 reflects the conservatism of ENEC’s management and board of directors, as well as our local, federal, and international stakeholders, all of who stand firmly united in the belief that long-term sustainable operations begin with strict adherence to nuclear safety.

"We believe that our continuous focus on quality and safety will position the UAE as a trusted contributor to the community of nuclear operators around the world.”

The Barakah Nuclear Energy Plant will feature four APR-1400 units. The first unit’s construction commenced in 2012 and at full operational capacity, the four units will be able to cater to one-fourth of the country’s power requirements.