India’s Bharat Heavy Electricals (BHEL) has secured a contract from Nepalese firm SJVN Arun-3 Power Development (SAPDC) to implement the 900MW Arun-3 Hydroelectric project.
Located in the Sankhuwasabha district, the project is expected to improve Nepal’s installed power capacity and support the country’s vision of utilising its vast hydropower potential for accelerated economic development.
How well do you really know your competitors?
Access the most comprehensive Company Profiles on the market, powered by GlobalData. Save hours of research. Gain competitive edge.
Thank you!
Your download email will arrive shortly
Not ready to buy yet? Download a free sample
We are confident about the unique quality of our Company Profiles. However, we want you to make the most beneficial decision for your business, so we offer a free sample that you can download by submitting the below form
By GlobalDataUnder the Rs5.36bn ($80m) deal, BHEL will be responsible for designing, engineering, manufacturing, supply, erection and commissioning of electromechanical equipment, which includes four vertical 225MW Francis turbines and generator sets.
For this project, BHEL will be manufacturing turbines, generators, generator transformers, control systems, bus ducts and other associated equipment at its India-based facilities.
The erection and commissioning works will be undertaken by BHEL’s Power Sector Northern Region and 400kV GIS will be executed by Transmission Business Group.
Upon completion, the Arun-3 Hydroelectric Project will be the largest hydropower project in the country.
BHEL entered the Nepalese energy market in 1980 by supplying and commissioning two 30MW Hydro Generating sets for the Kulekhani-I Hydro Power Project.
The company is currently executing hydro projects with capacities exceeding 2.7GW in Nepal and nearly 2.9GW in Bhutan.