Wuxi Combined Cycle Power Plant is an 800MW gas fired power project. It is located in Jiangsu, China. The project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in September 2018.

Project Type Total Capacity (MW) Active Capacity (MW) Pipeline Capacity (MW) Project Status Project Location Project Developer
Thermal 800 800 Active Jiangsu, China Pacific Oil & Gas

Description

The project was developed by Pacific Oil & Gas and is currently owned by East Asia Power (Wuxi).

It is a Combined Cycle Gas Turbine (CCGT) power plant that is used for Peakload.

The project cost is $1,518.72m.

Development Status

How well do you really know your competitors?

Access the most comprehensive Company Profiles on the market, powered by GlobalData. Save hours of research. Gain competitive edge.

Company Profile – free sample

Thank you!

Your download email will arrive shortly

Not ready to buy yet? Download a free sample

We are confident about the unique quality of our Company Profiles. However, we want you to make the most beneficial decision for your business, so we offer a free sample that you can download by submitting the below form

By GlobalData
Visit our Privacy Policy for more information about our services, how we may use, process and share your personal data, including information of your rights in respect of your personal data and how you can unsubscribe from future marketing communications. Our services are intended for corporate subscribers and you warrant that the email address submitted is your corporate email address.

The project got commissioned in September 2018.

Contractors Involved

Siemens was selected as the turbine supplier for thermal power project. The project consists of 4 turbines.

Siemens supplied SGen5-2000H electric generator for the Wuxi Combined Cycle Power Plant (Wuxi Combined Cycle Power Plant Unit I).

Siemens supplied SGen5-2000H electric generator for the Wuxi Combined Cycle Power Plant (Wuxi Combined Cycle Power Plant Unit II).

Siemens is the O&M contractor for thermal power project for a period of 9 years.

About Pacific Oil & Gas

Pacific Oil & Gas Ltd (PO & G) is an energy resource company that offers energy investment services. The company operates through business segments such as oil and gas, power and LNG. Its midstream and downstream operations include development of LNG receiving terminals and large-scale combined cycle gas turbine power plants in China. PO & G’s upstream activities comprise exploration, development and production of oil and gas in Indonesia. The company operates owns and operates the Xiamen CCGT power plant located in Xiamen. It has its presence throughout China, Singapore, Hong Kong and Indonesia. PO & G is headquartered in Beijing, China.

Methodology

All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.