Tierfehd is a 141MW hydro power project. It is located on Limmernboden river/basin in Switzerland. The project is currently active. It has been developed in single phase. The project commenced construction in 2005.

Project Type Total Capacity (MW) Active Capacity (MW) Pipeline Capacity (MW) Project Status Project Location Project Developer
Hydropower 141 141 Active Switzerland

Description

The project is currently owned by Kraftwerke Linth-Limmern.

Tierfehd is a pumped storage project. The total number of penstocks, pipes or long channels that carry water down from the hydroelectric reservoir to the turbines inside the actual power station, are 4 in number. The project generated 700 GWh of electricity.

Development Status

The project commenced construction in 2005.

Contractors Involved

Andritz Hydro was selected as the turbine supplier for the hydro power project. The company provided 4 units of pelton turbines, each with 35MW nameplate capacity.

Andritz Hydro supplied electric generator(s) for the project.

Methodology

All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.