Sydvastlanken N Barkeryd – Hallsberg Line is a 400kV overhead line from Sydvastlanken N Barkeryd, Orebro, Sweden, to Hallsberg, Orebro, Sweden.
Construction works on the Sydvastlanken N Barkeryd – Hallsberg Line started in 2014 and the project was commissioned in 2015.
Description
The Sydvastlanken N Barkeryd – Hallsberg Line, which is an overhead line, is being operated by Svenska Kraftnat. The Sydvastlanken N Barkeryd – Hallsberg Line is a new line. The line carries alternating current (AC).
Sydvastlanken N Barkeryd – Hallsberg Line project development status
The development of the Sydvastlanken N Barkeryd – Hallsberg Line project was approved by Swedish Energy Markets Inspectorate in 2014 and the project works were completed in 2015.
How well do you really know your competitors?
Access the most comprehensive Company Profiles on the market, powered by GlobalData. Save hours of research. Gain competitive edge.
Thank you!
Your download email will arrive shortly
Not ready to buy yet? Download a free sample
We are confident about the unique quality of our Company Profiles. However, we want you to make the most beneficial decision for your business, so we offer a free sample that you can download by submitting the below form
By GlobalDataAbout Svenska Kraftnat
Svenska Kraftnat (Svenska) is a state-owned electric utility. It develops, operates, and maintains the national transmission system in Sweden. The company balances production and consumption of electricity system in the country. It also carries out electricity contingency planning and is financed through government funding. Svenska conducts research and development to increase the transmission network’s operational reliability, efficiency and sustainability. The company constructs communications network for telecommunications and data for maintaining operational reliability in the grid. It has offices in Sundsvall and Solleftea. Svenska is headquartered in Sundbyberg, Sweden.
Methodology
All publicly-announced T&D Line & Substation projects included in this analysis are drawn from GlobalData’s Power IC. The information regarding the projects is sourced through secondary information sources such as country specific utility players, company news and reports, statistical organisations, regulatory body, government planning reports and their publications and is further validated through primary from various stakeholders such as power utility companies, consultants, energy associations of respective countries, government bodies and professionals from leading players in the power sector.