Solhom is a 200MW hydro power project. It is located on Kvina river/basin in Agder, Norway. The project is currently active. It has been developed in single phase. Post completion of construction, the project got commissioned in 1974.

Project Type Total Capacity (MW) Active Capacity (MW) Pipeline Capacity (MW) Project Status Project Location Project Developer
Hydropower 200 200 Active Agder, Norway

Description

Lyse Produksjon, Statkraft, Skagerrak Energi and Agder Energi are currently owning the project having ownership stake of 41.1%, 32.1%, 14.6% and 12.2% respectively.

Solhom is a reservoir based project. The gross head of the project is 210m. The project generated 669 GWh of electricity.

The hydro power project consists of 2 turbines, each with 100MW nameplate capacity.

The project has 2 electric generators installed at the site. The generator capacity is 125 MVA.

How well do you really know your competitors?

Access the most comprehensive Company Profiles on the market, powered by GlobalData. Save hours of research. Gain competitive edge.

Company Profile – free sample

Thank you!

Your download email will arrive shortly

Not ready to buy yet? Download a free sample

We are confident about the unique quality of our Company Profiles. However, we want you to make the most beneficial decision for your business, so we offer a free sample that you can download by submitting the below form

By GlobalData
Visit our Privacy Policy for more information about our services, how we may use, process and share your personal data, including information of your rights in respect of your personal data and how you can unsubscribe from future marketing communications. Our services are intended for corporate subscribers and you warrant that the email address submitted is your corporate email address.

Development Status

The project got commissioned in 1974.

Methodology

All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.