Shady Oaks Project is a 109.5MW onshore wind power project. It is located in Illinois, the US. The project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in June 2012.

Project Type Total Capacity (MW) Active Capacity (MW) Pipeline Capacity (MW) Project Status Project Location Project Developer
Onshore 109.5 109.5 Active Illinois, the US Mainstream Renewable Power

Description

The project was developed by Mainstream Renewable Power and is currently owned by Algonquin Power & Utilities.

The project generates 364,000MWh electricity and supplies enough clean energy to power 30,000 households.

Development Status

The project is currently active. The project got commissioned in June 2012.

How well do you really know your competitors?

Access the most comprehensive Company Profiles on the market, powered by GlobalData. Save hours of research. Gain competitive edge.

Company Profile – free sample

Thank you!

Your download email will arrive shortly

Not ready to buy yet? Download a free sample

We are confident about the unique quality of our Company Profiles. However, we want you to make the most beneficial decision for your business, so we offer a free sample that you can download by submitting the below form

By GlobalData
Visit our Privacy Policy for more information about our services, how we may use, process and share your personal data, including information of your rights in respect of your personal data and how you can unsubscribe from future marketing communications. Our services are intended for corporate subscribers and you warrant that the email address submitted is your corporate email address.

Power Purchase Agreement

The power generated from the project is sold to Commonwealth Edison under a power purchase agreement for a period of 20 years.

Contractors Involved

M. A. Mortenson and Sargent & Lundy were selected to render EPC services for the wind power project.

Shady Oaks Project (Shady Oaks Project IA) is equipped with Xinjiang Goldwind Science & Technology GW 1.5/82 turbines. The phase consists of 68 turbines with 1.5MW nameplate capacity.

Shady Oaks Project (Shady Oaks Project IB) is equipped with Xinjiang Goldwind Science & Technology GW 2.5/100 turbines. The phase consists of 3 turbines with 2.5MW nameplate capacity.

Goldwind USA lnc is the O&M contractor for the wind power project for a period of 20 years.

Broadwind Energy has supplied towers for the wind power project.

About Mainstream Renewable Power

Mainstream Renewable Power Ltd (Mainstream) is the renewable energy developer. The company carries out the development, finance, construction, and operation of large-scale renewable energy plants. It also develops and builds onshore, and offshore wind and solar power plants. Mainstream sold its projects to global utilities such as EDF Group and Orsted; and infrastructure funds, pension funds, and global brands. It has partnership with governments, developers, communities and financers. The company operates through its offices across Ireland, Vietnam, the Philippines, Canada, Egypt, Ghana, Senegal, the US, Chile and South Africa, among others. Mainstream is headquartered in Sandyford, Dublin, Ireland.

Methodology

All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.