Ribatejo Power Station is a 1,200MW gas fired power project. It is located in Lisbon, Portugal. The project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in 2004.
Project Type | Total Capacity (MW) | Active Capacity (MW) | Pipeline Capacity (MW) | Project Status | Project Location | Project Developer | Thermal | 1,200 | 1,200 | – | Active | Lisbon, Portugal |
---|
Description
The project is currently owned by Energias de Portugal.
It is a combined cycle gas turbine (ccgt) power plant.
Development Status
The project got commissioned in 2004.

US Tariffs are shifting - will you react or anticipate?
Don’t let policy changes catch you off guard. Stay proactive with real-time data and expert analysis.
By GlobalDataContractors Involved
PROMANEC – Engineering & Construction and Siemens were selected to render EPC services for the gas fired power project.
Ribatejo Power Station (Ribatejo Power Station Block I) is equipped with Siemens SGT5-4000F gas turbine. The phase consists of 1 gas turbine with 265MW nameplate capacity.
Ribatejo Power Station (Ribatejo Power Station Block I) is equipped with Siemens SST5-3000 steam turbine. The phase consists of 1 steam turbine with 135MW nameplate capacity.
Ribatejo Power Station (Ribatejo Power Station Block II) is equipped with Siemens SGT5-4000F gas turbine. The phase consists of 1 gas turbine with 265MW nameplate capacity.
Ribatejo Power Station (Ribatejo Power Station Block II) is equipped with Siemens SST5-3000 steam turbine. The phase consists of 1 steam turbine with 135MW nameplate capacity.
Ribatejo Power Station (Ribatejo Power Station Block III) is equipped with Siemens SGT5-4000F gas turbine. The phase consists of 1 gas turbine with 265MW nameplate capacity.
Ribatejo Power Station (Ribatejo Power Station Block III) is equipped with Siemens SST5-3000 steam turbine. The phase consists of 1 steam turbine with 135MW nameplate capacity.
Siemens supplied SGen5-2000H, Hydrogen Cooled electric generator for the Ribatejo Power Station (Ribatejo Power Station Block I).
Siemens supplied SGen5-2000H, Hydrogen Cooled electric generator for the Ribatejo Power Station (Ribatejo Power Station Block II).
Siemens supplied SGen5-2000H, Hydrogen Cooled electric generator for the Ribatejo Power Station (Ribatejo Power Station Block III).
Siemens Heat Transfer Technology supplied steam boiler for the Ribatejo Power Station (Ribatejo Power Station Block II).
Siemens Heat Transfer Technology supplied steam boiler for the Ribatejo Power Station (Ribatejo Power Station Block III).
Methodology
All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.