Prai 2 Combined Cycle Power Plant is a 1,071.43MW gas fired power project. It is located in Penang, Malaysia. The project is currently active. It has been developed in single phase. Post completion of construction, the project got commissioned in February 2016.

Project Type Total Capacity (MW) Active Capacity (MW) Pipeline Capacity (MW) Project Status Project Location Project Developer
Thermal 1,071.43 1,071.43 Active Penang, Malaysia TNB Northern Energy Sdn

Description

The project is developed and owned by TNB Northern Energy Sdn.

It is a Combined Cycle Gas Turbine (CCGT) power plant.

The project cost is $811.528m.

Development Status

The project got commissioned in February 2016.

Contractors Involved

Samsung C&T was selected to render EPC services for the gas fired power project.

Siemens was selected as the turbine supplier for the Gas fired project. The company provided 2 units of SGT5-8000H gas turbines.

Siemens was selected as the turbine supplier for the Gas fired project. The company provided 2 units of SST-5000 steam turbines.

Siemens supplied SGen-3000W electric generator for the project.

Doosan Heavy Industries & Construction supplied steam boiler for the project.

TNB Repair and Maintenance Sdn is the O&M contractor for thermal power project.

Methodology

All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.