Windpark Hanze is a 90MW onshore repowered wind power project. It is planned in Flevoland, Netherlands. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently at the under construction stage. It will be developed in a single phase. The project construction is likely to commence in 2022 and is expected to enter into commercial operation in 2024. Buy the profile here.
Description
The project is being developed by Windkoepel Groen.
The project is expected to generate 350,000MWh electricity and supply enough clean energy to power 115,000 households. The project is expected to offset 350,000t of carbon dioxide emissions (CO2) a year.
The project will have 166m high towers.
Development status
The project construction is expected to commence from 2022. Subsequent to that it will enter into commercial operation by 2024.
Power purchase agreement
The power generated from the project will be sold to Vattenfall under a power purchase agreement for a period of 15 years. The offtake capacity is expected to be 78MW.
Contractors involved
GE Renewable Energy will be the turbine supplier for the wind power project. The company is expected to provide 15 units of 6.0-164 turbines, each with 6MW nameplate capacity.
GE Renewable Energy is expected to perform operations and maintenance for the wind power project for a period of 25 years.
For more details on Windpark Hanze, buy the profile here.
About Windkoepel Groen
Windkoepel Groen BV (Windkoepel) generates, transmits and distributes electricity using renewable sources. Windkoepel s headquartered in the Netherland.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.