Wallsee-Mitterkirchen is a 210MW hydro power project. It is located on Danube river/basin in Lower Austria, Austria. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. The project construction commenced in 1965 and subsequently entered into commercial operation in 1968. Buy the profile here.
Description
The project is developed and owned by VERBUND Hydro Power.
Wallsee-Mitterkirchen is a run-of-river project. The gross head of the project is 10.8m. The project generated 1,342.26 MWh of electricity.
Development status
The project construction commenced in 1965 and subsequently entered into commercial operation in 1968.
Contractors involved
The turbines for the hydro power project have been supplied by Nydqvist & Holm and Voith Hydro Holding.
Andritz Hydro supplied electric generator(s) for the project. The generator capacity is 42.5 MVA.
Andritz Hydro supplied electric generator(s) for the project. The generator capacity is 44 MVA.
For more details on Wallsee-Mitterkirchen, buy the profile here.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.