Votkinskaya is a 1,120MW hydro power project. It is planned on Kama river/basin in Perm Krai, Russia. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently at the partially active stage. It will be developed in multiple phases. The project construction is likely to commence in 1957 and is expected to enter into commercial operation in 1961. Buy the profile here.
Description
The project is being developed and currently owned by RusHydro. The company has a stake of 100%.
Votkinskaya is a reservoir based project. The net head of the project will be 17.5m.
Development status
The project construction is expected to commence from 1957. Subsequent to that it will enter into commercial operation by 1961.
Contractors involved
Votkinskaya (Votkinskaya Rehabilitated (Unit-1)) will be equipped with Power Machines kaplan turbine. The phase consists of 1 turbine with 115MW nameplate capacity.
Votkinskaya (Votkinskaya Rehabilitated (Unit-10)) will be equipped with Power Machines kaplan turbine. The phase consists of 1 turbine with 115MW nameplate capacity.
Votkinskaya (Votkinskaya Rehabilitated (Unit-2)) will be equipped with Power Machines kaplan turbine. The phase consists of 1 turbine with 115MW nameplate capacity.
Votkinskaya (Votkinskaya Rehabilitated (Unit-3)) will be equipped with Power Machines kaplan turbine. The phase consists of 1 turbine with 115MW nameplate capacity.
Votkinskaya (Votkinskaya Rehabilitated (Unit-4)) will be equipped with Power Machines kaplan turbine. The phase consists of 1 turbine with 115MW nameplate capacity.
Votkinskaya (Votkinskaya Rehabilitated (Unit-5)) will be equipped with Power Machines kaplan turbine. The phase consists of 1 turbine with 115MW nameplate capacity.
Votkinskaya (Votkinskaya Rehabilitated (Unit-7)) will be equipped with Power Machines kaplan turbine. The phase consists of 1 turbine with 115MW nameplate capacity.
Votkinskaya (Votkinskaya Rehabilitated (Unit-8)) will be equipped with Power Machines kaplan turbine. The phase consists of 1 turbine with 115MW nameplate capacity.
Votkinskaya (Votkinskaya Under Rehab) will be equipped with Power Machines kaplan turbines. The phase consists of 2 turbines with 100MW nameplate capacity.
Power Machines will be the generator supplier for the hydro power project. The project consists of 10 turbines.
For more details on Votkinskaya, buy the profile here.
About RusHydro
RusHydro is an electric utility. The company's primary activities include the generation of electricity and heat from renewable sources such as water, solar, wind, and geothermal energy. It generates electricity and capacity, and transmits, distributes, and sells it on wholesale and retail basis. The company generates electricity using various sources such as hydro, ocean, wind, solar and geothermal. RusHydro also sells heat energy. Its services cater to a wide range of customers, from individual households to large industrial enterprises, across various sectors. The company services cover a vast area, from St. Petersburg to the Primorye Territory, and from the Chukotka Autonomous Area to the Republic of Dagestan. RusHydro is headquartered in Moscow, Russia.
Data Insights