Unchahar Thermal Power Station Stage I-III is a 1,050MW coal fired power project. It is located in Uttar Pradesh, India. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in November 1988. Buy the profile here.
Description
The project is currently owned by NTPC with a stake of 100%.
It is a Steam Turbine power plant that is used for Baseload. The power plant run on dual-fuel. The primary fuel being used to power the plant is coal. In case of shortage of coal the plant can also run on Heavy Fuel Oil, Light Diesel Oil. The fuel is procured from North Karanpura Coal Fields.
The project generated 7,622,000MWh of electricity.
Development status
The project got commissioned in November 1988.
Contractors involved
Unchahar Thermal Power Station Stage I-III (Unchahar Thermal Power Plant Stage I Unit I) is equipped with Bharat Heavy Electricals steam turbine. The phase consists of 1 steam turbine with 210MW nameplate capacity.
Unchahar Thermal Power Station Stage I-III (Unchahar Thermal Power Plant Stage I Unit II) is equipped with Bharat Heavy Electricals steam turbine. The phase consists of 1 steam turbine with 210MW nameplate capacity.
Unchahar Thermal Power Station Stage I-III (Unchahar Thermal Power Plant Stage II Unit I) is equipped with Bharat Heavy Electricals steam turbine. The phase consists of 1 steam turbine with 210MW nameplate capacity.
Unchahar Thermal Power Station Stage I-III (Unchahar Thermal Power Plant Stage II Unit II) is equipped with Bharat Heavy Electricals steam turbine. The phase consists of 1 steam turbine with 210MW nameplate capacity.
Unchahar Thermal Power Station Stage I-III (Unchahar Thermal Power Plant Stage III) is equipped with Bharat Heavy Electricals steam turbine. The phase consists of 1 steam turbine with 210MW nameplate capacity.
Bharat Heavy Electricals supplied electric generator for the Unchahar Thermal Power Station Stage I-III (Unchahar Thermal Power Plant Stage I Unit I).
Bharat Heavy Electricals supplied electric generator for the Unchahar Thermal Power Station Stage I-III (Unchahar Thermal Power Plant Stage I Unit II).
Bharat Heavy Electricals supplied electric generator for the Unchahar Thermal Power Station Stage I-III (Unchahar Thermal Power Plant Stage II Unit I).
Bharat Heavy Electricals supplied electric generator for the Unchahar Thermal Power Station Stage I-III (Unchahar Thermal Power Plant Stage II Unit II).
Bharat Heavy Electricals supplied electric generator for the Unchahar Thermal Power Station Stage I-III (Unchahar Thermal Power Plant Stage III).
Bharat Heavy Electricals supplied steam boiler for the Unchahar Thermal Power Station Stage I-III (Unchahar Thermal Power Plant Stage I Unit I).
Bharat Heavy Electricals supplied steam boiler for the Unchahar Thermal Power Station Stage I-III (Unchahar Thermal Power Plant Stage I Unit II).
Bharat Heavy Electricals supplied steam boiler for the Unchahar Thermal Power Station Stage I-III (Unchahar Thermal Power Plant Stage II Unit I).
Bharat Heavy Electricals supplied steam boiler for the Unchahar Thermal Power Station Stage I-III (Unchahar Thermal Power Plant Stage II Unit II).
Bharat Heavy Electricals supplied steam boiler for the Unchahar Thermal Power Station Stage I-III (Unchahar Thermal Power Plant Stage III).
NTPC is the O&M contractor for thermal power project.
For more details on Unchahar Thermal Power Station Stage I-III, buy the profile here.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.