The Tharparkar Power Plant is 1,320MW coal fired power project. It is planned in Sindh, Pakistan. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently at the partially active stage. It will be developed in multiple phases. Post completion of the construction, the project is expected to get commissioned in March 2019. Buy the profile here.
Description
The project is being developed by Engro Powergen Thar and is currently owned by Sindh Engro Coal Mining with a stake of 100%.
It is a Steam Turbine power plant. The fuel will be procured from Thar Coal Block-II.
Development status
Post completion of the construction, the project is expected to get commissioned in March 2019.
Contractors involved
Tharparkar Power Plant (Tharparkar Power Plant Phase I Unit I) will be equipped with Dongfang Electric steam turbines.
Tharparkar Power Plant (Tharparkar Power Plant Phase I Unit II) will be equipped with Dongfang Electric steam turbines.
Dongfang Electric is likely to be the supplier of steam boiler for the Tharparkar Power Plant (Tharparkar Power Plant Phase I Unit I).
Dongfang Electric is likely to be the supplier of steam boiler for the Tharparkar Power Plant (Tharparkar Power Plant Phase I Unit II).
For more details on Tharparkar Power Plant, buy the profile here.
About Engro Powergen Thar
Engro Powergen Thar Pvt Ltd, a subsidiary of Engro Corp Ltd, operates within the energy and utilities industry, specifically focusing on the commodity of power. It is involved in the generation, transmission, and distribution of electrical power for residential, commercial, and industrial use. The company is headquartered in Karachi, Sindh, Pakistan.