Tenaska Lindsay Hill Generating Station is a 939.4MW gas fired power project. It is located in Alabama, the US. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. Post completion of construction, the project got commissioned in May 2002. Buy the profile here.
Description
The project is developed and owned by Tenaska Alabama Partners. The company has a stake of 100%.
It is a Combined Cycle Gas Turbine (CCGT) power plant. The power plant run on dual-fuel. The primary fuel being used to power the plant is natural gas. In case of shortage of natural gas the plant can also run on Distillate Fuel Oil. The fuel is procured from Williams Gas Pipeline - Transco.
The project generated 2,414,473MWh of electricity.
Development status
The project got commissioned in May 2002.
Contractors involved
GE Power was selected as the turbine supplier for the Gas fired project. The company provided 1 steam turbine with 390.1MW nameplate capacity.
GE Power was selected as the turbine supplier for the Gas fired project. The company provided 3 units of 7F.04 gas turbines, each with 183.1MW nameplate capacity.
GE Power supplied electric generator for the project.
GE Power supplied electric generator for the project.
Hamon Deltak supplied steam boiler for the project.
Hamon Deltak supplied steam boiler for the project.
For more details on Tenaska Lindsay Hill Generating Station, buy the profile here.
About Tenaska Alabama Partners
Tenaska Alabama Partners, L.P. (Tenaska Alabama) is a renewable energy company, based in the US. The company builds and operates gas- fueled generating stations. It operates combined-cycle facility with a generating capacity of 885 MW located at Alabama. Tenaska Alabama was formed to build and own the facility of Tenaska Inc. The company has fuel conversion services agreement with BE Alabama LLC. Its fuels are owned and supplied by the customers, which is converted into electricity and marketed throughout the Southeast region's wholesale power market. Tenaska Alabama has three General Electric Frame 7FA gas turbines, three heat recovery steam generators and one General Electric steam turbine, which include catalytic emission controls. The company operates as subsidiary of Tenaska Inc. Tenaska Alabama is headquartered in Billingsley, Alabama, the US.