Suizhong Power Station Phase I & II is a 3,600MW coal fired power project. It is located in Liaoning, China. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in 2000. Buy the profile here.
Description
Others, China Shenhua Energy and CLP Holdings are currently owning the project having ownership stake of 50%, 35% and 15% respectively.
It is a Steam Turbine power plant that is used for Baseload.
The project generated 15,092,000MWh of electricity.
Development status
The project got commissioned in 2000.
Contractors involved
American Electric Power and Teploelektroproekt Kharkov Branch were selected to render engineering procurement construction services for the coal fired power project.
The Coal fired project have been supplied by Dongfang Turbine, Electrosila and Leningradsky Metallichesky Zavod.
The electric generators for the project were procured from Electrosila and Leningradsky Metallichesky Zavod.
Taganrog Boiler-Making Works Krasny Kotelshchik supplied steam boiler for the Suizhong Power Station Phase I & II (Suizhong Power Station Phase I & II Unit I).
Taganrog Boiler-Making Works Krasny Kotelshchik supplied steam boiler for the Suizhong Power Station Phase I & II (Suizhong Power Station Phase I & II Unit I).
Taganrog Boiler-Making Works Krasny Kotelshchik supplied steam boiler for the Suizhong Power Station Phase I & II (Suizhong Power Station Phase I & II Unit I).
Taganrog Boiler-Making Works Krasny Kotelshchik supplied steam boiler for the Suizhong Power Station Phase I & II (Suizhong Power Station Phase I & II Unit II).
Taganrog Boiler-Making Works Krasny Kotelshchik supplied steam boiler for the Suizhong Power Station Phase I & II (Suizhong Power Station Phase I & II Unit II).
Taganrog Boiler-Making Works Krasny Kotelshchik supplied steam boiler for the Suizhong Power Station Phase I & II (Suizhong Power Station Phase I & II Unit II).
Dongfang Boiler Group supplied steam boiler for the Suizhong Power Station Phase I & II (Suizhong Power Station Phase I & II Unit III).
Dongfang Boiler Group supplied steam boiler for the Suizhong Power Station Phase I & II (Suizhong Power Station Phase I & II Unit III).
Dongfang Boiler Group supplied steam boiler for the Suizhong Power Station Phase I & II (Suizhong Power Station Phase I & II Unit III).
Dongfang Boiler Group supplied steam boiler for the Suizhong Power Station Phase I & II (Suizhong Power Station Phase I & II Unit IV).
Dongfang Boiler Group supplied steam boiler for the Suizhong Power Station Phase I & II (Suizhong Power Station Phase I & II Unit IV).
Dongfang Boiler Group supplied steam boiler for the Suizhong Power Station Phase I & II (Suizhong Power Station Phase I & II Unit IV).
For more details on Suizhong Power Station Phase I & II, buy the profile here.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.