Stalowa Wola Combined Cycle Power Plant is a 450MW gas fired power project. It is located in Subcarpathia, Poland. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. The project construction commenced in 2012 and subsequently entered into commercial operation in October 2020. Buy the profile here.
Description
The project was developed by Elektrocieplownia Stalowa Wola. The project is co-owned by Polskie Gornictwo Naftowe i Gazownictwo and Tauron Polska Energia, with their respective ownership stake of 50% each.
It is a CCGT with Cogen power plant.
The project generated 3,500GWh of electricity.
Development status
The project construction commenced in 2012 and subsequently entered into commercial operation in October 2020.
Contractors involved
The Gas fired project have been supplied by Doosan Skoda Power and GE Power.
The electric generators for the project were procured from Doosan Skoda Power and GE Power.
Amec Foster Wheeler supplied steam boiler for the project.
Amec Foster Wheeler supplied steam boiler for the project.
Amec Foster Wheeler supplied steam boiler for the project.
GE Power is the O&M contractor for thermal power project for a period of 12 years.
For more details on Stalowa Wola Combined Cycle Power Plant, buy the profile here.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.