St Pantaleon is a 52MW hydro power project. It is located on Enns river/basin in Lower Austria, Austria. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. The project construction commenced in 1960 and subsequently entered into commercial operation in 1965. Buy the profile here.
Description
The project was developed by Ennskraftwerke. The project is co-owned by Energie AG Oberosterreich Trading and VERBUND Hydro Power, with their respective ownership stake of 50% each.
St Pantaleon is a run-of-river project. The project generated 261.6 GWh of electricity.
Development status
The project construction commenced in 1960 and subsequently entered into commercial operation in 1965.
Contractors involved
Voith Hydro Holding was selected as the turbine supplier for the hydro power project. The company provided 1 unit of kaplan turbine with 27.29MW nameplate capacity.
The electric generators for the project were procured from ELIN Motoren and Siemens.
For more details on St Pantaleon, buy the profile here.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.