Sichuan Luzhou Chuannan Power Generation Plant Phase I is a 1,200MW coal fired power project. It is located in Sichuan, China. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in December 2007. Buy the profile here.
Description
The project is currently owned by Sichuan Luzhou Chuannan Power Generation with a stake of 100%.
It is a Steam Turbine power plant.
Development status
The project got commissioned in December 2007.
Contractors involved
Dongfang Turbine was selected as the turbine supplier for thermal power project. The project consists of 2 units of N600-16.67/538/538 turbines, each with 600MW nameplate capacity.
DEC Dongfang Electric Machinery supplied QFSN-600-2-22C electric generator for the Sichuan Luzhou Chuannan Power Generation Plant Phase I (Sichuan Luzhou Chuannan Power Generation Plant Phase I Unit I).
DEC Dongfang Electric Machinery supplied QFSN-600-2-22C electric generator for the Sichuan Luzhou Chuannan Power Generation Plant Phase I (Sichuan Luzhou Chuannan Power Generation Plant Phase I Unit II).
Dongfang Boiler Group supplied steam boiler for the Sichuan Luzhou Chuannan Power Generation Plant Phase I (Sichuan Luzhou Chuannan Power Generation Plant Phase I Unit I).
Dongfang Boiler Group supplied steam boiler for the Sichuan Luzhou Chuannan Power Generation Plant Phase I (Sichuan Luzhou Chuannan Power Generation Plant Phase I Unit II).
For more details on Sichuan Luzhou Chuannan Power Generation Plant Phase I, buy the profile here.