Seoincheon Combined Cycle Power Plant is a 1,800MW gas fired power project. It is located in Incheon, South Korea. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. The project construction commenced in 1990 and subsequently entered into commercial operation in November 1992. Buy the profile here.
Description
The project is currently owned by Korea Western Power with a stake of 100%.
It is a Combined Cycle Gas Turbine (CCGT) power plant that is used for Peakload.
Development status
The project construction commenced in 1990 and subsequently entered into commercial operation in November 1992.
Contractors involved
GE Power was selected as the turbine supplier for the Gas fired project. The company provided 8 steam turbines, each with 75MW nameplate capacity.
GE Power was selected as the turbine supplier for the Gas fired project. The company provided 8 units of 7FA+e gas turbines, each with 150MW nameplate capacity.
GE Power supplied electric generator for the project.
GE Power supplied electric generator for the project.
Doosan Enerbility supplied steam boiler for the project.
Doosan Enerbility supplied steam boiler for the project.
For more details on Seoincheon Combined Cycle Power Plant, buy the profile here.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.