Se San 4A is a 63MW hydro power project. It is located on Se San river/basin in Gia Lai, Vietnam. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. The project construction commenced in 2004 and subsequently entered into commercial operation in 2011. Buy the profile here.
Description
The project is developed and owned by Sesan 4A Hydroelectric.
The gross head and net head of the project are 17.7m and 12.2m respectively. The total number of penstocks, pipes or long channels that carry water down from the hydroelectric reservoir to the turbines inside the actual power station, are 3 in number. The penstock length is 41.72m. The project generated 314.8 GWh of electricity.
Development status
The project construction commenced in 2004 and subsequently entered into commercial operation in 2011.
Contractors involved
Anhui Anmec Import & Export was selected as the turbine supplier for the hydro power project. The company provided 3 turbines, each with 21.65MW nameplate capacity.
Anhui Anmec Import & Export supplied 21 electric generators for the project. The generator capacity is 3 MVA.
For more details on Se San 4A, buy the profile here.
About Sesan 4A Hydroelectric
Sesan 4A Hydroelectric JSC is a Vietnam-based hydropower generator. The Company is primarily engaged in the construction and operation of Sesan 4A hydroelectric power plant located in Gia Lai province. SHJC also involves in constructing power lines, related structures and industrial facilities, along with wholesaling construction materials, such as bricks, stones and sand. It is headquartered in Pleiku, Vietnam.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.