Santo Antonio – Alto Minho I is a 32MW onshore wind power project. It is located in Viana do Castelo, Portugal. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. Post completion of construction, the project got commissioned in 2008. Buy the profile here.
Description
The project was developed by Ventominho - Energias Renovaveis and is currently owned by Finerge Gestao de Projectos Energeticos.
The project generates 62,000MWh electricity thereby offsetting 23,942.1t of carbon dioxide emissions (CO2) a year.
The project has 64m high towers.
Development status
The project is currently active. The project got commissioned in 2008.
Contractors involved
Enercon was selected as the turbine supplier for the wind power project. The company provided 16 units of E-70 turbines, each with 2MW nameplate capacity.
For more details on Santo Antonio - Alto Minho I, buy the profile here.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.