Qidong H3 Offshore Wind Farm is a 300MW offshore wind power project. The project is located in Yellow Sea, Jiangsu, China. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. The project construction commenced in 2020 and subsequently entered into commercial operation in December 2021. Buy the profile here.
Description
The project was developed by Qidong Huaerrui Wind Power Technology. Jiangsu Huawei Wind Power and Qidong Huaerrui Wind Power Technology are currently owning the project.
The wind turbines in the project are installed on fixed foundations. An array of monopile foundations feature in the project.
The project generates 81,747MWh electricity thereby offsetting 663,100t of carbon dioxide emissions (CO2) a year.
Development status
The project is currently active. The project construction commenced in 2020 and subsequently entered into commercial operation in December 2021.
Contractors involved
East China Survey and Design Institute and Jiangsu Warwick Wind Power were selected to render engineering procurement construction services for the wind power project.
Shanghai Electric Wind Power Equipment was selected as the turbine supplier for the wind power project.
For more details on Qidong H3 Offshore Wind Farm, buy the profile here.