Prai 2 Combined Cycle Power Plant is a 1,071.43MW gas fired power project. It is located in Penang, Malaysia. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. Post completion of construction, the project got commissioned in February 2016. Buy the profile here.
Description
The project is developed and owned by TNB Northern Energy Sdn.
It is a Combined Cycle Gas Turbine (CCGT) power plant.
Development status
The project got commissioned in February 2016.
Contractors involved
Samsung C&T was selected to render engineering procurement construction services for the gas fired power project.
Siemens was selected as the turbine supplier for the Gas fired project. The company provided 2 units of SGT5-8000H gas turbines.
Siemens was selected as the turbine supplier for the Gas fired project. The company provided 2 units of SST-5000 steam turbines.
Siemens supplied SGen-3000W electric generator for the project.
Siemens supplied SGen-3000W electric generator for the project.
Doosan Enerbility supplied steam boiler for the project.
Doosan Enerbility supplied steam boiler for the project.
TNB Repair and Maintenance Sdn is the O&M contractor for thermal power project.
For more details on Prai 2 Combined Cycle Power Plant, buy the profile here.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.