Porce III is a 660MW hydro power project. It is located on Porce river/basin in Antioquia, Colombia. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. The project construction commenced in 2004 and subsequently entered into commercial operation in 2010. Buy the profile here.
Description
The project is currently owned by Empresas Publicas De Medellin.
The hydro reservoir capacity is 170 million cubic meter. The project generated 3,416.4 GWh of electricity.
Development status
The project construction commenced in 2004 and subsequently entered into commercial operation in 2010.
Contractors involved
IMPSA was selected as the turbine supplier for the hydro power project. The company provided 4 units of francis turbines.
Toshiba Energy Systems and Solutions supplied 4 electric generators for the project. The generator capacity is 218 MVA.
IMPSA International is the O&M contractor for the hydro power project.
For more details on Porce III, buy the profile here.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.