Paiton 9 Power Plant is a 660MW coal fired power project. It is located in East Java, Indonesia. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. Post completion of construction, the project got commissioned in 2012. Buy the profile here.
Description
The project is currently owned by PT Pembangkitan Jawa-Bali.
It is a Steam Turbine power plant.
Development status
The project got commissioned in 2012.
Contractors involved
Harbin Electric was selected to render engineering procurement construction services for the coal fired power project.
Harbin Turbine was selected as the turbine supplier for the Coal fired project. The company provided 1 steam turbine with 660MW nameplate capacity.
Harbin Electric supplied electric generator for the project.
Harbin Electric supplied electric generator for the project.
Harbin Electric supplied electric generator for the project.
Harbin Boiler supplied steam boiler for the project.
Harbin Boiler supplied steam boiler for the project.
Harbin Boiler supplied steam boiler for the project.
Harbin Electric International and PT Pembangkitan Jawa-Bali were contracted to render operations & maintenance services for the project.
For more details on Paiton 9 Power Plant, buy the profile here.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.