Muara Karang Power Plant Unit 4 and 5 is a 400MW gas fired power project. It is located in Jakarta, Indonesia. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in 1981. Buy the profile here.
Description
The project is currently owned by PT Pembangkitan Jawa-Bali with a stake of 100%.
It is a Steam Turbine power plant. The fuel is procured from PT Nusantara Regas BP Berau Ltd. (Tangguh Gas Field).
Development status
The project got commissioned in 1981.
Contractors involved
Mitsubishi Power was selected as the turbine supplier for thermal power project. The project consists of 2 units of TCDF turbines, each with 200MW nameplate capacity.
Mitsubishi Power supplied electric generator for the Muara Karang Power Plant Unit 4 and 5 (Muara Karang Power Plant Unit 4).
Mitsubishi Power supplied electric generator for the Muara Karang Power Plant Unit 4 and 5 (Muara Karang Power Plant Unit 5).
For more details on Muara Karang Power Plant Unit 4 and 5, buy the profile here.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.