Mosenergo TPP-27 Combined Cycle Power Plant is a 900MW gas fired power project. It is located in Moscow, Russia. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in November 2007. Buy the profile here.

Smarter leaders trust GlobalData

Report-cover

Data Insights Mosenergo TPP-27 Combined Cycle Power Plant

Buy the Profile

Data Insights

The gold standard of business intelligence.

Find out more

Description

The project is currently owned by Mosenergo with a stake of 100%.

It is a CCGT with Cogen power plant. The fuel is procured from Gazprom.

Development status

The project got commissioned in November 2007.

Contractors involved

Mosenergo TPP-27 Combined Cycle Power Plant (Mosenergo TPP-27 Combined Cycle Power Plant Block I) is equipped with Power Machines steam turbine;gas turbine. The phase consists of 1 steam turbine;gas turbine with 130MW nameplate capacity.

Mosenergo TPP-27 Combined Cycle Power Plant (Mosenergo TPP-27 Combined Cycle Power Plant Block I) is equipped with Power Machines GTE-160 gas turbines. The phase consists of 2 gas turbines with 160MW nameplate capacity.

Mosenergo TPP-27 Combined Cycle Power Plant (Mosenergo TPP-27 Combined Cycle Power Plant Block II) is equipped with Power Machines steam turbine. The phase consists of 1 steam turbine with 130MW nameplate capacity.

Mosenergo TPP-27 Combined Cycle Power Plant (Mosenergo TPP-27 Combined Cycle Power Plant Block II) is equipped with Power Machines GTE-160 gas turbines. The phase consists of 2 gas turbines with 160MW nameplate capacity.

Power Machines supplied electric generator for the Mosenergo TPP-27 Combined Cycle Power Plant (Mosenergo TPP-27 Combined Cycle Power Plant Block I).

Power Machines supplied electric generator for the Mosenergo TPP-27 Combined Cycle Power Plant (Mosenergo TPP-27 Combined Cycle Power Plant Block II).

Podolsk Machine-Building Plant ZIO supplied steam boiler for the Mosenergo TPP-27 Combined Cycle Power Plant (Mosenergo TPP-27 Combined Cycle Power Plant Block I).

Podolsk Machine-Building Plant ZIO supplied steam boiler for the Mosenergo TPP-27 Combined Cycle Power Plant (Mosenergo TPP-27 Combined Cycle Power Plant Block II).

For more details on Mosenergo TPP-27 Combined Cycle Power Plant, buy the profile here.

This content was updated on 14 October 2024

Data Insights

From

The gold standard of business intelligence.

Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.

GlobalData

GlobalData, the leading provider of industry intelligence, provided the underlying research used to produce this article.

This information is drawn from GlobalData’s Power Intelligence Center, which provides detailed profiles of over 170,000 active, planned and under construction power plants worldwide from announcement through to operation across all technologies and countries worldwide.