Mori Hanol is a 64MW hydro power project. It is planned on Tons river/basin in Uttarakhand, India. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently at the permitting stage. It will be developed in a single phase. Post completion of the construction, the project is expected to get commissioned in 2026. Buy the profile here.
Description
The project is being developed by THDCIL-UJVNL Energy. THDC India and Uttarakhand Jal Vidyut Nigam are currently owning the project having ownership stake of 74% and 26% respectively.
The hydro reservoir capacity is planned to be 1.017 million cubic meter. The gross head and net head of the project will be 113m and 103m respectively. The total number of penstocks, pipes or long channels that carry water down from the hydroelectric reservoir to the turbines inside the actual power station, is expected to be 1 in number. The penstock length will be 203m. The penstock diameter will be 4m. The project is expected to generate 318.89 GWh of electricity.
The hydro power project consists of 2 turbines, each with 32MW nameplate capacity.
The project will have 2 electric generators installed at the project site. The generator capacity is likely to be 42 MVA.
Development status
Post completion of the construction, the project is expected to get commissioned in 2026.
For more details on Mori Hanol, buy the profile here.
About THDCIL-UJVNL Energy
THDCIL-UJVNL Energy Co Ltd is engaged in a production and maintenance of hydro power project that specializes in electricity, gas, steam and air condition supply. The company is headquartered in Dehradun, Uttarakhand, India.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.