Huaneng Haimen Power Plant is a 4,144MW coal fired power project. It is located in Guangdong, China. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in July 2009. Buy the profile here.
Description
The project is currently owned by Huaneng Power International.
It is a Steam Turbine power plant.
The project generated 12,270,000MWh of electricity.
Development status
The project got commissioned in July 2009.
Power purchase agreement
The power generated from the project is sold to Guangdong Fine Electric Power under a power purchase agreement.
Contractors involved
Huaneng Haimen Power Plant (Huaneng Haimen Power Plant Unit I) is equipped with Dongfang Turbine N1036-25.0/600/600, Single Four-cylinder, Back-pressure, Reheat, Condensing Type steam turbine. The phase consists of 1 steam turbine with 1,036MW nameplate capacity.
Huaneng Haimen Power Plant (Huaneng Haimen Power Plant Unit II) is equipped with Dongfang Turbine N1036-25.0/600/600, Single Four-cylinder, Back-pressure, Reheat, Condensing Type steam turbine. The phase consists of 1 steam turbine with 1,036MW nameplate capacity.
Huaneng Haimen Power Plant (Huaneng Haimen Power Plant Unit III) is equipped with Dongfang Turbine steam turbine. The phase consists of 1 steam turbine with 1,036MW nameplate capacity.
Huaneng Haimen Power Plant (Huaneng Haimen Power Plant Unit IV) is equipped with Dongfang Turbine steam turbine. The phase consists of 1 steam turbine with 1,036MW nameplate capacity.
DEC Dongfang Electric Machinery supplied QFSN 1000-27 electric generator for the Huaneng Haimen Power Plant (Huaneng Haimen Power Plant Unit I).
DEC Dongfang Electric Machinery supplied QFSN 1000-27 electric generator for the Huaneng Haimen Power Plant (Huaneng Haimen Power Plant Unit II).
Mitsubishi Power supplied steam boiler for the Huaneng Haimen Power Plant (Huaneng Haimen Power Plant Unit I).
Mitsubishi Power supplied steam boiler for the Huaneng Haimen Power Plant (Huaneng Haimen Power Plant Unit II).
Dongfang Boiler Group supplied steam boiler for the Huaneng Haimen Power Plant (Huaneng Haimen Power Plant Unit III).
Dongfang Boiler Group supplied steam boiler for the Huaneng Haimen Power Plant (Huaneng Haimen Power Plant Unit IV).
For more details on Huaneng Haimen Power Plant, buy the profile here.