Hoort Wind Farm is a 57.6MW onshore wind power project. It is located in Mecklenburg-Vorpommern, Germany. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in December 2019. Buy the profile here.
Description
The project is developed by LOSCON and Mea Energieagentur Mecklenburg-Vorpommern. These companies also have ownership stakes in the project.
The project generates 150,000MWh of electricity.
The Hoort Wind Farm (Hoort_LOSCON I-A), has 141m high towers.
The Hoort Wind Farm (Hoort_LOSCON I-B), has 141m high towers.
The Hoort Wind Farm (Hoort_Mea IA), has 141m high towers.
The Hoort Wind Farm (Hoort_Mea IB), has 141m high towers.
The Hoort Wind Farm (Hoort_Mea IC), has 141m high towers.
Development status
The project is currently active. The project got commissioned in December 2019.
Contractors involved
Nordex was selected as the turbine supplier for the wind power project. The project consists of 16 units of N117/3600 turbines, each with 3.6MW nameplate capacity.
Nordex is the O&M contractor for the wind power project. The operation and maintenance contract commenced from 2019, for a period of 15 years.
For more details on Hoort Wind Farm, buy the profile here.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.