Dadaepo Offshore Wind Power Project is a 96MW offshore wind power project. It is planned in Sea of Japan (East Sea), Busan, South Korea. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently at the permitting stage. It will be developed in a single phase. The project construction is likely to commence in 2025 and is expected to enter into commercial operation in 2028. Buy the profile here.
Description
The project is being developed by Busan Offshore Wind Power and is currently owned by Corio Generation with a stake of 100%. The turbines will be mounted on fixed type foundations.
The wind power project consists of 12 turbines, each with 8MW nameplate capacity.
Development status
The project construction is expected to commence from 2025. Subsequent to that it will enter into commercial operation by 2028.
For more details on Dadaepo Offshore Wind Power Project, buy the profile here.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.