Capivara is a 619MW hydro power project. It is located on Paranapanema river/basin in Sao Paulo, Brazil. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. The project construction commenced in 1971 and subsequently entered into commercial operation in 1977. Buy the profile here.
Description
The project is currently owned by China Three Gorges Brasil Energia with a stake of 63%.
Capivara is a reservoir based project. The project generated 3,871.44 GWh of electricity.
Development status
The project construction commenced in 1971 and subsequently entered into commercial operation in 1977.
Contractors involved
Power Machines was selected as the turbine supplier for the hydro power project. The company provided 4 units of francis turbines, each with 163MW nameplate capacity.
Power Machines supplied 4 electric generators for the project. The generator capacity is 178 MVA.
For more details on Capivara, buy the profile here.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.