Caojing Combined Cycle Power Plant is a 600MW gas fired power project. It is located in Shanghai, China. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in August 2005. Buy the profile here.
Description
The project is currently owned by Shanghai Caojing Power Generation with a stake of 100%.
It is a CCGT with Cogen power plant that is used for Peakload. The fuel is procured from Chaidamu Basin of Qinghai, Tarim Basin of Xinjiang and Shanganning Region..
Development status
The project got commissioned in August 2005.
Contractors involved
Black & Veatch, East China Electric Power Design Institute and Shanghai Electric Power Construction were selected to render engineering procurement construction services for the gas fired power project.
GE Power was selected as the turbine supplier for the Gas fired project. The company supplied 9001FA++ Gas Turbine, Steam Turbine model steam turbine;gas turbines for the project.
GE Power supplied electric generator for the project.
GE Power supplied electric generator for the project.
GE Power supplied electric generator for the project.
AE&E Nanjing Boiler supplied steam boiler for the project.
AE&E Nanjing Boiler supplied steam boiler for the project.
AE&E Nanjing Boiler supplied steam boiler for the project.
General Electric is the O&M contractor for thermal power project for a period of 25 years.
For more details on Caojing Combined Cycle Power Plant, buy the profile here.