Bradisor is an 115MW hydro power project. It is located on Lotru river/basin in Valcea, Romania. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. The project construction commenced in 1973 and subsequently entered into commercial operation in 1982. Buy the profile here.
Description
The project is currently owned by SPEEH Hidroelectrica.
Bradisor is a reservoir based project. The gross head and net head of the project are 156m and 128.5m respectively. The project generated 228 GWh of electricity.
Development status
The project construction commenced in 1973 and subsequently entered into commercial operation in 1982.
Contractors involved
UCM Resita was selected as the turbine supplier for the hydro power project. The company provided 2 units of francis turbines, each with 57.5MW nameplate capacity.
Hydro Engineering supplied 2 electric generators for the project. The generator capacity is 62 MVA.
For more details on Bradisor, buy the profile here.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.