Barney Davis Energy Center is a 730.2MW gas fired power project. It is located in Texas, the US. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in July 1976. Buy the profile here.
Description
The project is currently owned by Talen Energy Supply with a stake of 100%.
It is a Combined Cycle Gas Turbine (CCGT) power plant. The fuel is procured from ONYX GAS MARKETING CO.
Development status
The project got commissioned in July 1976.
Contractors involved
Barney Davis Energy Center (Barney Davis Energy Center Unit I) is equipped with Siemens Energy steam turbine. The phase consists of 1 steam turbine with 351MW nameplate capacity.
Barney Davis Energy Center (Barney Davis Energy Center Unit II) is equipped with GE Power 7F.04 gas turbine. The phase consists of 1 gas turbine with 189.6MW nameplate capacity.
Barney Davis Energy Center (Barney Davis Energy Center Unit III) is equipped with GE Power 7F.04 gas turbine. The phase consists of 1 gas turbine with 189.6MW nameplate capacity.
Nooter/Eriksen supplied steam boiler for the Barney Davis Energy Center (Barney Davis Energy Center Unit II).
Nooter/Eriksen supplied steam boiler for the Barney Davis Energy Center (Barney Davis Energy Center Unit III).
For more details on Barney Davis Energy Center, buy the profile here.