Ambarli Dual Fuel Combined Cycle Power Plant is an 820MW dual-fuel fired power project. It is located in Istanbul, Turkey. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. Post completion of construction, the project got commissioned in 2013. Buy the profile here.
Description
The project is currently owned by Elektrik Uretim with a stake of 100%.
It is a Combined Cycle Gas Turbine (CCGT) power plant. The power plant run on dual-fuel. The primary fuel being used to power the plant is natural gas. In case of shortage of natural gas the plant can also run on Diesel.
Development status
The project got commissioned in 2013.
Contractors involved
EKON Industry Construction and Trade, PROKON Engineering and Consultancy, PROKON Manufacturing and Erection and Proterm Enerji were selected to render engineering procurement construction services for the dual-fuel fired power project.
The Dual-Fuel fired project have been supplied by Escher Wyss and Siemens Energy.
Siemens Energy supplied SGen5-100A-2p electric generator for the project.
Siemens Energy supplied SGen5-100A-2p electric generator for the project.
Siemens Energy supplied SGen5-100A-2p electric generator for the project.
Siemens Energy supplied SGen5-100A-2p electric generator for the project.
Andritz supplied steam boiler for the project.
Andritz supplied steam boiler for the project.
Andritz supplied steam boiler for the project.
Andritz supplied steam boiler for the project.
For more details on Ambarli Dual Fuel Combined Cycle Power Plant, buy the profile here.