Alexander is a 69MW hydro power project. It is located on Nipigon river/basin in Ontario, Canada. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. The project construction commenced in 1927 and subsequently entered into commercial operation in 1930. Buy the profile here.
Description
The project was developed by Hydro-Electric Power Commission of Ontario and is currently owned by Ontario Power Generation with a stake of 100%.
The project generated 450 GWh of electricity.
Development status
The project construction commenced in 1927 and subsequently entered into commercial operation in 1930.
Contractors involved
S. Morgan Smith-Inglis was selected as the turbine supplier for the hydro power project. The company provided 3 units of francis turbines, each with 12.75MW nameplate capacity.
S. Morgan Smith-Inglis was selected as the turbine supplier for the hydro power project. The company provided 2 units of francis turbines, each with 13.5MW nameplate capacity.
Canadian General Electric supplied 5 electric generators for the project.
For more details on Alexander, buy the profile here.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.