Oyster Bay Wind Farm is a 147.6MW onshore wind power project. It is located in Eastern Cape, South Africa. The project is currently active. It has been developed in single phase. The project construction commenced in 2020 and subsequently entered into commercial operation in 2021.
Project Type | Total Capacity (MW) | Active Capacity (MW) | Pipeline Capacity (MW) | Project Status | Project Location | Project Developer | Onshore | 147.6 | 147.6 | – | Active | Eastern Cape, South Africa | Enel Green Power RSA; RES Southern Africa |
---|
Description
The project was developed by Enel Green Power RSA and RES Southern Africa. Enel Green Power RSA and Khana Energy are currently owning the project having ownership stake of 60% and 35% respectively.
The project generates 568GWh electricity and supplies enough clean energy to power 130,000 households, offsetting 590,000t of carbon dioxide emissions (CO2) a year. The project cost is $201.563m.
The project has 91.50m high towers.
Development Status

US Tariffs are shifting - will you react or anticipate?
Don’t let policy changes catch you off guard. Stay proactive with real-time data and expert analysis.
By GlobalDataThe project is currently active. The project construction commenced in 2020 and subsequently entered into commercial operation in 2021.
Power Purchase Agreement
The power generated from the project is sold to Eskom Holdings SOC under a power purchase agreement. The power is sold at the rate of $0.048kWh for a period of 20 years. The contracted capacity is 147.6MW.
Contractors Involved
Vestas Wind Systems was selected to render EPC services for the wind power project.
Vestas Wind Systems was selected as the turbine supplier for the wind power project. The company provided 41 units of V117-3.45 MW turbines, each with 3.6MW nameplate capacity.
Vestas Wind Systems is the O&M contractor for the wind power project for a period of 5 years.
Methodology
All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.