Kostolac power station

China plans to sign a $600m deal with Serbia, which will help the latter construct an additional unit at the Kostolac coal-fired power plant.

Kostolac general manager Dragan Jovanovic was quoted by Reuters as saying that the construction of the new 350MW unit will take five years.

Serbia will repay a $608m loan from China over 20 years. The financing agreement will allow a grace period of seven years and charge 2.5% as interest annually.

State-run utility Elektroprivreda Srbije (EPS) and the Serbian Government will provide the remaining $107m for the project.

A $1.25bn upgrade is already underway at Kostolac, which is mainly being financed by Export-Import Bank of China.

"The construction of the new 350MW unit will take five years."

The upgrade is expected to extend the life span of the coal-fired plant and boost its power production capacity. The present B1 and B2 units currently use outdated technology, which means they fail to operate to their full capacity.

How well do you really know your competitors?

Access the most comprehensive Company Profiles on the market, powered by GlobalData. Save hours of research. Gain competitive edge.

Company Profile – free sample

Thank you!

Your download email will arrive shortly

Not ready to buy yet? Download a free sample

We are confident about the unique quality of our Company Profiles. However, we want you to make the most beneficial decision for your business, so we offer a free sample that you can download by submitting the below form

By GlobalData
Visit our Privacy Policy for more information about our services, how we may use, process and share your personal data, including information of your rights in respect of your personal data and how you can unsubscribe from future marketing communications. Our services are intended for corporate subscribers and you warrant that the email address submitted is your corporate email address.

Ageing coal-fired plants are the primary sources of energy generation in Serbia, providing up to two-third of its supply.

Serbia had to import large quantities of power and coal earlier in May, after flooding hit the country’s biggest power plant, Reuters reported.


Image: Power Station Kostolac A. Photo: courtesy of Mazbln / Wikipedia.

Energy