Mosenergo TEP-25 Power Plant is a 1,370MW gas fired power project. It is located in Moscow, Russia. The project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in January 1975.

Project Type Total Capacity (MW) Active Capacity (MW) Pipeline Capacity (MW) Project Status Project Location Project Developer
Thermal 1,370 1,370 Active Moscow, Russia

Description

The project is currently owned by Mosenergo with a stake of 100%.

It is a steam turbine with cogen power plant that is used for Baseload. The power plant run on dual-fuel. The primary fuel being used to power the plant is natural gas. In case of shortage of natural gas the plant can also run on Fuel Oil.

The project generated 8,256,000MWh of electricity.

Development Status

How well do you really know your competitors?

Access the most comprehensive Company Profiles on the market, powered by GlobalData. Save hours of research. Gain competitive edge.

Company Profile – free sample

Thank you!

Your download email will arrive shortly

Not ready to buy yet? Download a free sample

We are confident about the unique quality of our Company Profiles. However, we want you to make the most beneficial decision for your business, so we offer a free sample that you can download by submitting the below form

By GlobalData
Visit our Privacy Policy for more information about our services, how we may use, process and share your personal data, including information of your rights in respect of your personal data and how you can unsubscribe from future marketing communications. Our services are intended for corporate subscribers and you warrant that the email address submitted is your corporate email address.

The project got commissioned in January 1975.

Contractors Involved

Mosenergo TEP-25 Power Plant (Mosenergo TEP-25 Power Plant Unit I) is equipped with Leningradsky Metallichesky Zavod PT-60-130 steam turbine. The phase consists of 1 steam turbine with 60MW nameplate capacity.

Mosenergo TEP-25 Power Plant (Mosenergo TEP-25 Power Plant Unit II) is equipped with Leningradsky Metallichesky Zavod PT-60-130 steam turbine. The phase consists of 1 steam turbine with 60MW nameplate capacity.

Mosenergo TEP-25 Power Plant (Mosenergo TEP-25 Power Plant Unit III) is equipped with Leningradsky Metallichesky Zavod T-250-240 steam turbine. The phase consists of 1 steam turbine with 250MW nameplate capacity.

Mosenergo TEP-25 Power Plant (Mosenergo TEP-25 Power Plant Unit IV) is equipped with Leningradsky Metallichesky Zavod T-250-240 steam turbine. The phase consists of 1 steam turbine with 250MW nameplate capacity.

Mosenergo TEP-25 Power Plant (Mosenergo TEP-25 Power Plant Unit V) is equipped with Leningradsky Metallichesky Zavod T-250-240 steam turbine. The phase consists of 1 steam turbine with 250MW nameplate capacity.

Mosenergo TEP-25 Power Plant (Mosenergo TEP-25 Power Plant Unit VI) is equipped with Leningradsky Metallichesky Zavod T-250-240 steam turbine. The phase consists of 1 steam turbine with 250MW nameplate capacity.

Mosenergo TEP-25 Power Plant (Mosenergo TEP-25 Power Plant Unit VII) is equipped with Leningradsky Metallichesky Zavod T-250-240 steam turbine. The phase consists of 1 steam turbine with 250MW nameplate capacity.

Electrosila supplied electric generator for the project.

Taganrog Boiler-Making Works Krasny Kotelshchik supplied steam boiler for the Mosenergo TEP-25 Power Plant (Mosenergo TEP-25 Power Plant Unit III).

Taganrog Boiler-Making Works Krasny Kotelshchik supplied steam boiler for the Mosenergo TEP-25 Power Plant (Mosenergo TEP-25 Power Plant Unit IV).

Taganrog Boiler-Making Works Krasny Kotelshchik supplied steam boiler for the Mosenergo TEP-25 Power Plant (Mosenergo TEP-25 Power Plant Unit V).

Taganrog Boiler-Making Works Krasny Kotelshchik supplied steam boiler for the Mosenergo TEP-25 Power Plant (Mosenergo TEP-25 Power Plant Unit VI).

Taganrog Boiler-Making Works Krasny Kotelshchik supplied steam boiler for the Mosenergo TEP-25 Power Plant (Mosenergo TEP-25 Power Plant Unit VII).

Methodology

All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.