Livorno Ferraris Power Plant is an 805MW gas fired power project. It is located in Piedmont, Italy. The project is currently active. It has been developed in single phase. Post completion of construction, the project got commissioned in September 2008.
Project Type | Total Capacity (MW) | Active Capacity (MW) | Pipeline Capacity (MW) | Project Status | Project Location | Project Developer | Thermal | 805 | 805 | – | Active | Piedmont, Italy |
---|
Description
EP Power Europe and BKW Italia are currently owning the project having ownership stake of 75% and 25% respectively.
It is a Combined Cycle Gas Turbine (CCGT) power plant.
The project cost is $629.719m.
Development Status
How well do you really know your competitors?
Access the most comprehensive Company Profiles on the market, powered by GlobalData. Save hours of research. Gain competitive edge.
Thank you!
Your download email will arrive shortly
Not ready to buy yet? Download a free sample
We are confident about the unique quality of our Company Profiles. However, we want you to make the most beneficial decision for your business, so we offer a free sample that you can download by submitting the below form
By GlobalDataThe project got commissioned in September 2008.
Contractors Involved
Siemens was selected as the turbine supplier for the Gas fired project. The company provided 2 units of SGT5-4000F gas turbines.
Siemens was selected as the turbine supplier for the Gas fired project. The company provided 1 unit of SST5-5000 steam turbine.
Siemens supplied SGen5-1000A electric generator for the project.
STF supplied steam boiler for the project.
Methodology
All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.